This site is located in the High Street, Rottingdean, Brighton.

Entacom were approached by Novus Property Developments to tender for the supply and installation of video door entry system for eight houses with a gated entrance.

Entacom meet Novus on site to carry out a full survey of the site and to find out the requirements of the system, Novus required video hands free units on each floor and a entrance panel by each front door, also a video entrance panel by the main gate. Entacom sent a written quotation for a Comelit system with Planux hands free units. After winning the tender the installation lasted for about two weeks, regular meetings were held during the installation to update Novus with our progress. The installation was managed and commissioned by Will Hobden (Manager) and installed by Steve Forest (Engineer). On completion of the installation the hand over was carried out by Will Hobden issuing the OM manual. The gated entrance is still going through planning permission.